Project

Cruise Terminal 1 – Cruise Mooring Bollards

Timescale

Nov 23 – Mar 24

Value

£650,000

Client

Port of Dover

Port of Dover

Introduction

This project was undertaken at the Western Docks at the Port of Dover and was driven by safety and operational factors.

The Port carried out a review of the adequacy of mooring bollards at Cruise Terminal 1 (CT1) using mooring analysis software to identify additional and replacement bollards required to ensure the berth could safely accommodate vessels up to 265m.

Following the mooring analysis, it was necessary to design and install additional cope bollards along the cope line of CT1 to provide a greater number of bollards for vessels to use as well as removing existing low-capacity bollards.

Port of Dover Cruise Terminal 1 – Cruise Mooring Bollards

The Project

The works included mooring analysis & design, removal of 8nr existing mooring bollards (30-60t), breakout granite capping beam in locations of 3nr new bollards, install grouted anchors into CT1 quay wall, install the reinforcement for bollard foundations and pour new concrete foundations, and installation of 3nr new 75t mooring bollards and surrounding high friction surfacing.

The works were procured via the Port’s existing NEC3 contractor framework, utilising an ECC form of contract. Moreton & Partners led the procurement and commercial activities to support Port of Dover’s engineering team to deliver this key project.

Services Provided

  • Tender analysis / contract award
  • Pre and post contract administration
  • NEC3 Framework & ECC
  • Cost planning
  • Project financial control and reporting
  • Change management
  • Final account