Project
Chilmington Green Pumping Station & Mains Reinforcement
Timescale
Client
Southern Water
The Project
Moreton & Partners provided both project management and commercial services.
- Major delay inflicted on the programme due to access constrainst
- Third party involvement – UKPN/Road civil contractor/Ashford council/Housing developer/Highways England/ SGN
- Wet well (shaft contractor) – size, construction tecnique
- Mech & Electrical fit out
Land access negotiation - Waterbrook – resurrection of mothballed site
- UTX drill – under track crossing
Services Provided
- Leading members of a collaborative project team
- All contract practice
- Headed up regular risk reduction and mitigation meetings between the parties
- Project financial control and reporting
- Programme review and acceptance (NEC)
- Quantification and costing change
- Measurement of refurbished asset (Confined space entry)