Project
Timescale
27 Months
Value
£25,801,824
Client
South East Water
![South East Water](https://moretonqs.co.uk/wp-content/uploads/2022/11/south-east-water-logo.jpg)
Introduction
SEW Water Resource Management Plan (WRMP) scheme to deliver 20 ML/D into WRZ6 by 2025 from a newly constructed Butler Water Treatment works purchased from the former Aylesford Newsprint site, near Maidstone Kent.
Butler WTW is the first new state of the art water treatment works which, in partnership with J Murphy & Sons Ltd, has been built in Kent for over 18 years and will supply up to 20 million litres of drinking water a day to the local area.
Once built, the new water treatment works will represent a key investment for Kent and a vital part of South East Water’s plans to ensure it can continue to supply the area with tap water as the population grows.
![Port of Dover Cruise Terminal 1 – Cruise Mooring Bollards](https://moretonqs.co.uk/wp-content/uploads/2025/01/butler-wtw-cover.jpg)
The Project
The scheme involves the purchase of land and abstraction licences for the boreholes and the construction of a new water treatment works, and infrastructure to deliver a yield of up to 20 Ml/d which reduces the current reliance on Burham WTW. This scheme will improve resilience in supply.
The water treatment works will make use of two existing boreholes, pipework and storage tank already at the site, three new boreholes located north of the M20, and three new additional boreholes located south of the M20.
The new works includes wastewater handling, cartridge filters, GAC filtration, sodium hypochlorite and chlorine dioxide dosing, UV disinfection, standby generation, HV transformer and site power, contact tank, sedimentation tank and backwash tank, surge vessel and SEMD security.
SEW had engaged Murphys on a separate PSC contract to undertake the RIBA 3 design, which has been incorporated as the Contractor’s Design within the Engineering Construction Contract to deliver the scheme through to completion.
M&P have been engaged throughout, from feasibility and outline design phases to producing budget cost estimates and cost plans, contract preparation, managing risks and value engineering and carrying out regular commercial and programme meetings.
Key challenges to the project were obtaining the volumes of abstraction water to be able to commission the plant at 20 ML/D. Financial pressures from the Employer necessitating stop and restart work instructions and dealing with high levels of water ingress into deep excavations which required temporary discharge and abstraction licences and temporary works to recharge the aquifer.
Services Provided
- Regulated procurement
- Tender analysis / contract award
- Pre and post contract administration
- NEC3/Framework/PSC/ECC/
- Cost planning
- Risk management
- Project financial control and reporting
- Programme review and acceptance (NEC)
- Project management
- Programme management
- Change management
- Quantification and costing change